We were sent this by email today:
Scottish Water
Seafield Odour Improvement Plan 4 June 2010
On the horizon Veolia Water UK is
continuing to install covers on critical parts of the Seafield
Wastewater Treatment Works (WWTW) as promised, as part of odour
mitigation measures to meet the requirements of the
WRc recommended
abatement measures.
Installation of the weir covers on the
Primary Settlement Tanks is well underway and the installation team is
currently working on the weir covers for the second tank.
Installation
of high level pipe work has also recently begun, making visitors to the
site even more aware of the scale of the project.
Meet the
Partners
The stakeholders met Alex McTear, Veolia Project
Manager, and the project team once again. As well as receiving the
latest update on the progress of the project, key stakeholders also had a
tour of the latest works.
Committee Chair Kenny MacAskill, MSP
(pictured left) was particularly impressed by progress at the
plant:
"The upgrade of Seafield WWTW has been a long time
coming. No doubt, residents will be encouraged to hear that the project
is progressing and running to schedule.
Of course, there is
still some distance to travel and I appreciate that there may continue
to be difficulties while the works are carried out. However,
hopefully, the upgrade will provide a lasting solution to a long
standing problem"
Already completed
New elements of process equipment, including the first screenings handling plant, which removes rags and other waste
from the network, are now in position.
These will play an
important part in the day to day operation of the facility and ensure
that treatment equipment and other engineering assets do not become
snagged with sanitary products and other debris.
Items such as
sanitary products, cotton buds and nappies should be bagged and binned
with your household rubbish rather than flushed down the toilet. For
additional information on Scottish Water’s Bag It & Bin It campaign
please go to
www.scottishwater.co.uk/bagitbinit.
Installation
of new coarse screens and 6 millimetre fine screens, which prevent such
debris entering into the treatment process, is ongoing.
On schedule The multi million pounds project to address odour issues at the Seafield
WWTW remains on schedule. Construction of the inlet works is running
smoothly and is due for completion in November 2010, while the odour
improvement project is scheduled for completion by the late spring of
2011.
It will still be necessary for the local authority to
monitor the facility for a period following the completion of the works,
to ensure that the project is working satisfactorily in addressing
odour issues in the Leith area.
On the road
Veolia and Scottish Water have received praise from key local
stakeholders regarding the recent roadshow held at Ocean Terminal.
Speaking
about the day, local councillor Marjorie Thomas said:
"It was
good to see such a good turnout of officials taking the Seafield Project
to the public. So far progress has been good and communication very
good."
It was important for Scottish Water and Veolia Water to
engage with the wider Leith public in order to ascertain the variety of
views held by local customers. Feedback forms were given to shoppers,
and they were encouraged to express their opinions on the Seafield
Project.
For children passing through the shopping centre with
their parents there was the opportunity to win a bike. The prize winner,
drawn by Kenny MacAskill MSP, was Mrs Pentony from Leith.
The
latest news on Seafield WWTW is available at
www.scottishwater.co.uk/seafield.